Contract awarded for the replacement of Pier #11
March 2005

American Bridge/McLean Pier #11 Constructors, a joint venture between McLean Contracting Company and American Bridge were awarded the Replacement of Pier #11 project from NAVFAC Mid-Atlantic on March 1, 2005 for $91,552,110.00. The first phase of this project includes the demolition of a 1300 LF concrete pier structure, an 800 LF cellular breakwater system, as well as some miscellaneous timber piers. The second phase of this project includes the construction of a new 1600 LF double deck concrete carrier pier supported by 36” & 54” diameter prestressed concrete cylinder piles with a concrete relieving platform supported by 18” square concrete piles and a concrete sheetpile bulkhead. McLean Contracting Company’s portion of the work is $35,972,998.00, which includes all the demolition, piledriving and concrete work associated with the first level of the double deck pier and all the relieving platform work. Work to commence in the fall of 2005.